Installation and commissioning
 
1, users put the line, excavation, concrete pouring equipment according to the basic conditions and the local geological meteorological conditions, casting quality health should pay attention to the foundation, ensure the size and location of the right to the left, and to ensure the position and level of buried iron, error control within 1/1000, to carefully checked before installation.
2, inventory of all parts of the equipment, to ensure that the specifications, models, the number of accurate.
3, were assembled in a hot blast furnace, drying tower, hoisting machine, main fan, ventilator, electric control cabinet and other major components.
4, according to the basic position and the requirements of the overall image of the major components in place, and to ensure that the location of the center and the relative relationship.
5, School of inspection, to ensure that the installation position of the correct size, the hot blast furnace, drying tower, lifting machine, major components of the main fan, fan, electric cabinet hoisting, ensure the installation error is less than 1/1000, and reliable.
6, join the Department of smoke and air pipeline and the auxiliary.
7, each part of the motor and transmission parts in place, and put the wires, cables. And according to the technical requirements of masonry work.
8, the final part of the safety protection devices installed in place, and the overall quality of the installation of all checks and proofreading.
9, after the end of the installation of the transmission of the manual operation of the machine, check the true error can be carried out on the machine for a single test run.
No error can be used for on-line operation no-load operation 1-2 hour test 10, single, and oil to each lubricating part.
11, ignition, coal, the hot stove was smoked. 3-5 day, at this time, the main fan must be opened in order to avoid the empty furnace burning and destruction of the furnace body and heat exchange part.
12, and then began to clear the grain on the grain, and do a comprehensive inspection, eliminate hidden dangers, do a good job in the preparatory work.

Operation and maintenance:
 
1, drying operation is a joint operation of many people, must strengthen the organization and management, the establishment of full management of the captain, and the establishment of the effective rules and regulations, strict management.
2, the staff must be trained and assessed before the mount guard operation, and be responsible for their own work to coordinate the relationship between the various links.
3, mechanical and electrical personnel to do the inspection, timely processing problems in strict accordance with the mechanical and electrical properties and the use of the need to operate well.
4, the fireman to ensure normal combustion state of hot blast stove, to do qinguo Qin, Qin Qing, Tim, must first open the main fan start fan at the time of ignition, shutdown must stop the ventilator, the air temperature dropped to 40 degrees below and then stop the main fan.
5, grain personnel should stick to their posts, when the grain storage section must be filled with food, belt machine, cleaning machine, hoist the quick stop and start, should first open the hoisting machine, cleaning machine, finally to open belt machine, food personnel should always pay attention to the level of good food, not much food or food., resulting in the loss of.
6, each class must be on the rotating parts timely inspection and lubrication maintenance.
7, the heat exchanger and dust collector should be cleaned every week 1-2 times, in order to ensure the normal combustion.
8, a temporary stop should be discharged in grain drying, after the end of the period also will drain the grain and the Department of clean and good anti rust rain work, one to two times a year for maintenance, every two years should be a foreign table maintenance paint.